A six-week rambler rehab, kept in view.
See how an investor protects a cosmetic-remodel baseline, schedules every trade, and forecasts kitchen-opening risk before it threatens the targeted exit window and cash-on-cash return.
Acquisition
$450,000
Closed Sep 18 · value-add flip
Estimated ARV
$650,000
Target listing Nov 2
Rehab duration
6.0 weeks
Six-week critical path
Today's control point
Kitchen opening
Field condition controls rough-in release
02 · Protected baseline
The original plan stays intact.
RehabIQ keeps the approved starting point visible while the team evaluates a possible field condition. Forecasts help make decisions; they never rewrite history or become actuals.
Original baseline
$72,000
Approved before work began. Locked for comparison.
Revised forecast
$72,000
No forecasted changes approved.
Committed / actual to date
$19,500
Committed entries only. Final actuals are not known.
| Budget category | Original | Committed | Control note |
|---|---|---|---|
| Kitchen opening + peninsula | $11,000 | $6,200 | Forecasted hidden-condition review |
| Cabinets, counters + backsplash | $15,000 | $3,600 | Installation follows rough-in |
| Bath tile surround + vanity | $8,500 | $2,100 | Materials approved |
| Electrical panel + furnace | $12,000 | $4,500 | Rough-in dependency |
| Paint, doors, trim + lighting | $10,500 | $0 | Finishes phase |
| Exterior, fencing + cleanup | $6,000 | $2,000 | Site work underway |
| Appliances | $5,000 | $0 | Delivery coordinated |
| Contingency | $4,000 | $0 | Held at baseline |
03 · Live job schedule
Every trade, handoff, and risk in one six-week board.
This seeded contractor calendar is the project's critical path—not a live multi-user integration. Schedule confirmation and field-work status are intentionally tracked as separate signals.
Rambler Live Job Schedule
16 scheduled assignments · six-week critical path · seeded demo
Download the selected week as an .ics calendar export. This demo download does not provide live Google, Apple, or Outlook syncing.
Opening + rough-in
Tap an assignment to inspect its contractor handoff.
Critical path conflict to resolve
Kitchen framing must clear before electrical, HVAC, plumbing, and rough inspection. A hidden condition could collide with those confirmed/sent handoffs and squeeze the Oct 28 staging plus Oct 30 photography window.
04 · Change-order control
Approve a forecast without erasing the plan.
This decision simulates a kitchen-opening hidden condition. Approve it to update the revised budget and future schedule forecast; the locked original baseline and unknown actuals stay separate.
CO-01 · Kitchen opening
Possible framing and utility correction discovered while opening the wall. The scope is forecasted pending investor approval.
Forecasted cost
+$6,800
Forecasted schedule
+4 days
Affected handoff
Inspect / rough-in
Control rule
Original: $72,000 remains protected.
Revised: budget and planned dates change only after approval.
Actual: remains unknown until work and invoices are completed.
05 · Verify the work
Document each handoff before releasing the next crew.
The demo uses seeded documentation states to show how field photos, sign-off, and quality checks can support completion—not replace contractor coordination.
Kitchen opening documentation
Before-wall, framing, and utility-condition placeholders are queued against the critical path.
Listing-ready check
Staging and photography remain visible as separate scheduled assignments, so a finish delay is not hidden in a generic closeout list.
06 · Learn for next time
A completed rehab becomes better operating data.
At closeout, RehabIQ compares the protected original baseline with approved revisions and final actual results—then uses the gap to improve the next project.
Original budget
$72,000
Locked baseline
Revised forecast
$72,000
No forecast approved
Actual cost
Unknown
Project in progress
Schedule variance
Unknown
No delay confirmed